Sumamry of Events - Week of January JANUARY 19, 2009

The top tower section was delivered.The three blades got to Connecticut and had to wait until Tuesday January 27 to finish their move to the site due to restrictions on moving 'super loads' over CT highways Friday through Monday. The two remaining tower sections will arrive at Quonset Point, separately the weeks of Janaury 26 and February 2 and be staged for barge transport to Aquidneck Island. The final piece of electrical equipment, the 'recloser', required by the interconnect agreement with National Grid, is expected to arrive on February 3. The final major component, the Nacelle (that houses the main gnerator), is due to arrive Quonset about February 9. Power generation is expected on or about February 16, 2009.

See the full weekly report HERE (633 KB PDF).



Top Tower Section moves to the site (next 11 images)

1



















Internals of Top Tower Section, showinf ladders and electrical lines.


Portsmouth's Generator being assembled at the AAER plant at Bromont, Canada







To view some files, you may need AdobeTM Acrobat Reader. Get a FREE COPY at adobe.com.

© Copyright Porthsmouth Economic Development Committee - Sustainable Energy Subcomittee