SITE RESTORATION, LEVELING AND SEEDING CONDUCTED - Weeks of October 13 and 20, 2008
Civil engineering would is nearly completed with leveling of the surrounding
landscaping and seeding being completed. We are waiting the delivery of electrical transmission
components that are due in few weeks. Work continues to assemble our generator in Canada.
Although there are several potential suppliers on the list, we expect our turbines blades to
come from a company in Little Rock Arkansas. The tower is now expected to be supplied by a
manufacturer in Washington State. All major parts are expected to arrive on site in Mid December.
. Looking South - WTG Foundation and
Main Switchgear Foundation in foreground.
Looking North - WTG Foundation in distance .Access Road (looking E) .