CIVIL ENGINEERING AND ELECTRICAL WORK CONTINUES - Week of September 22, 2008
Laying and compacting of stone was commenced as the base for the access road and crane pad.
The remaining sections of the grounding grid were welded together. The small transformer providing service to
the tennis court lights was also installed (this was completed during daylight hours that prevented the need to
interrupt service to the courts at night). Redesign of the re-closure mechanism has been completed to comply
with National Grid's requirements for relay redundancy.
. New electrical pole
Welding of grounding grid .
. Access road from basketball courts
(Looking W)
Crane pad leveling (looking W)
. Access road (looking E from crane pad area)
. Crane pad area (Looking E) Cut throught trees in distance
is where access road cuts trough to the basketball courts.
Leveling of crane pad area (looking S) .